July 28th, 2020, CFD industrial area submarine drainage pipeline laying project undertaken by Timeast officially started! Representatives of Client, Contractor, Supervision party and Timeast General Manager and department leaders attended the ceremony. Timeast will complete the project with full enthusiasm and high-quality, return Contractor's trust with excellent projects, and compose a new chapter in offshore construction!
Client leader attended commencement ceremony; Timeast project manager introduced project situation
Project manager introduced pipeline and S-Lay Barge TIMEAST-601
Timeast Hard Workers
Group photo of young staff and experienced staff
CFD Industrial Area Submarine Drainage Pipeline Laying Project Introduction
Onshore pipeline 0.2km, offshore pipeline 1.37km. Pipeline procurement, anticorrosion, onshore and offshore pipeline installation, diffuser, fixed pile and apron installation, pre-trenching, backfilling, pigging and hydrotesting etc.