Congratulations on Shore Approach Pipeline Installation for Offshore Terminal of Niger to Benin Crude Oil Export Pipeline Project Completion

Jun. 08, 2022

Apr. 14th, 2022, shore approach pipelines have been successfully pulled into place. May. 15th, all construction tasks of two 28-inch shore approach pipelines have been completed. Each pipeline is about 500m long. Shore Approach Pipeline Installation for Offshore Terminal of Niger to Benin Crude Oil Export Pipeline Project was successfully completed.


Congratulations on Shore Approach Pipeline Installation for Offshore Terminal of Niger to Benin Crude Oil Export Pipeline Project Completion


Congratulations on Shore Approach Pipeline Installation for Offshore Terminal of Niger to Benin Crude Oil Export Pipeline Project Completion


The project is located in about 30km east of Benin COTONOU Port in West Africa. Two parallel pipelines of about 14.4km long will be laid from the landing end to the sea side. The offshore terminal is a single point mooring system of CALM type. Timeast is mainly responsible for the construction of two 28-inch offshore pipelines, each is about 500 meters. 


Main work scope: Pulling Site Construction, Shore Approach Submarine Pipeline Laying, Flooding, Post-trenching, Backfilling with Dredged Material, Site Reinstatement, etc.


Engineering department project team members lived up to their expectations, triumphantly returned to motherland’s embrace and reunited with their families safely.


Congratulations on Shore Approach Pipeline Installation for Offshore Terminal of Niger to Benin Crude Oil Export Pipeline Project Completion