Tianjin Timeast Offshore Engineering Co., Ltd.
Home >> Press >> News

Jidong Oilfield (Offshore Jacket and Platform Installation) Project Progressing Smoothly

Mar. 31, 2023


With winning the bid for Jidong Oilfield (Offshore Jacket and Platform Installation) Project, Timeast carried out the related organization and coordination work quickly, and made preparations for the construction in advance. After the completion of the offshore jacket fabrication, transportation and installation, the NP1-3P auxiliary platform upper block was successfully lifted in one time, which is the most difficult construction link of the project.


Jidong Oilfield (Offshore Jacket and Platform Installation) Project Progressing Smoothly

Offshore Jacket Loading and Transportation


Jidong Oilfield (Offshore Jacket and Platform Installation) Project Progressing Smoothly

TANYI 601 in Position


Jidong Oilfield (Offshore Jacket and Platform Installation) Project Progressing Smoothly

NP1-3 Wellhead Reconstruction Platform Block Installation


NP1-3P auxiliary platform is a 4-legged main pile jacket structure, the total weight is about 750 tons including the structure, module, crane and etc. To meet the above lifting capacity and adapt to the water depth and ensure the platform installation smoothly, after multiple comparisons, the lifting operation performed by a 1500T crane barge on the morning of the 20th. This large-scale offshore lifting operation requesting precise positioning and high accuracy combination for the upper block and jacket and multiple types of cooperation. The PMT of Timeast optimized the operation plan reasonably, seized the good weather window, and with the strong support of the company and leaders from all parties, Timeast achieved one-time successful lifting operation for the NP1-3P auxiliary platform upper block.


Jidong Oilfield (Offshore Jacket and Platform Installation) Project Progressing Smoothly

NP1-3P Auxiliary Platform Prefabrication Completion and Transportation


Jidong Oilfield (Offshore Jacket and Platform Installation) Project Progressing Smoothly

NP1-3P Auxiliary Platform Offshore Jacket Installation


Jidong Oilfield (Offshore Jacket and Platform Installation) Project Progressing Smoothly


Jidong Oilfield (Offshore Jacket and Platform Installation) Project Progressing Smoothly

NP1-3P Auxiliary Platform Upper Block Lifting



The PMT of Jidong Oilfield Project will keep accumulating the experiences of offshore platform and jacket installation in future construction, promoting the project a safe and stable progress, turning towards the final completion sprint of the project!