Project Introduction:

1.72km the submarine mixed transmission pipeline and 2.91km,10kv submarine cable laying, one simple offshore production platform and its supporting production and power supply & distribution facilities construction. 


Work Scope:

① NP1-1D jacket, trestle transportation and offshore installation (including but not limited to loading, protection, binding and fixing, transportation, cleaning; piling, pile head cutting, protection, cleaning, anti-corrosion repair, grouting, crown plate installation and other work);


② NP1-3P jacket, upper block of platform transportation and offshore installation (including but not limited to weighing, loading, protection, binding and fixing, transportation, monitoring and cleaning; piling, pile head cutting, protection, cleaning, anti-corrosion repair, grouting, crown plate installation, the upper block offshore installation and commissioning and other work; platform modification 15.642t).