Project Introduction

The project is located at Puti Island, Laoting County, between Jingtang Port and CFD Port, Tangshan City. The total installed capacity of the wind farm is 300MW, 75 units of wind turbine generator with single capacity of 4MW. 12 circuits are arranged for 35kV power collection line cables among 75 units of wind turbine generator, and a new 220kV offshore booster station is built by connecting 35kV submarine optic/electric composite cable to the site.


Work Scope:

220kV transmission ashore cables (3 sections, each is about 14210m in length, totaling 42.63km) and 35kV power collection line cables (75 sections, each is 940m-6845m in length, totaling 112.685km), both are submarine optic/electric composite cables.


Tangshan Laoting Puti Island Offshore Wind Farm 300MW Demonstration Project 35KV Submarine Photoelectric/Optical Composite Cable Laying Project (Year 2019)   Tangshan Laoting Puti Island Offshore Wind Farm 300MW Demonstration Project 35KV Submarine Photoelectric/Optical Composite Cable Laying Project (Year 2019)   Tangshan Laoting Puti Island Offshore Wind Farm 300MW Demonstration Project 35KV Submarine Photoelectric/Optical Composite Cable Laying Project (Year 2019)

Tangshan Laoting Puti Island Offshore Wind Farm 300MW Demonstration Project 35KV Submarine Photoelectric/Optical Composite Cable Laying Project (Year 2019)               Tangshan Laoting Puti Island Offshore Wind Farm 300MW Demonstration Project 35KV Submarine Photoelectric/Optical Composite Cable Laying Project (Year 2019)