Jidong Nanpu 1-29 Gas Storage Pilot Test Ground Engineering Injection Acquisition and Gathering Pipeline Project Lay Barge Construction Project has successfully completed offshore pipeline laying and started riser expansion bend installation.
Offshore pipeline laying is really difficult and requires high welding technology and equipment capacity. With water depth increase, seabed instability, low rock strength and many other factors, offshore pipeline laying technical difficulty has increased exponentially. During pipeline laying, there was an intertidal zone about 500 meters in construction area which increased lots of difficulties. Meanwhile, a new process is added, which started from both ends of the pipeline and horizontal ends tie-in pipe section. All project members rose to the challenges, and main construction lay barge "TIAN YI 601" successfully completed submarine pipeline laying task within the scheduled time. The smooth laying work made a good foundation for riser expansion bend installation, post-trenching and other project related work subsequently.
Offshore Pipeline Laying
Offshore Pipeline Abandonment
Tie-in
Nov. 22th, 2022, riser expansion bend installation is in full swing, Timeast provide parameter calculation and technical installation guidance to this work. During this installation process, it’s necessary to grasp expansion bend posture timely and accurately, and use effective control methods. The requirements for measurement, prefabrication, and installation accuracy are extremely high. Muddy water quality and poor visibility at construction site also increase the operation risk. At present, project team is fully aware of the difficulty and risk of expansion bend installation, pay high attention to the preparation and site work before installation, and is promoting the construction work in an orderly manner.
Riser Expansion Bend Prefabrication
Riser Expansion Bend Installation
Jidong Nanpu 1-29 Gas Storage Pilot Test Ground Engineering Injection Acquisition and Gathering Pipeline Project Lay Barge Construction Project team carries forward the craftsmanship spirit, takes root in project front line, adheres to green construction, and continues to accumulate experience in offshore engineering construction. In the future, we will pay close attention to project quality under the premise of ensuring safe construction, so as to promote post-trenching and backfilling operation in the next stage.