Tianjin Timeast Offshore Engineering Co., Ltd.
Home >> Our Services >> Submarine/Offshore Cable/Optical Cable Laying and Repairing

Chenghai 1-1 Platform Submarine Cable Laying Project (Year 2021—CNPC)

Share:

Project Description:

KP3.8~KP0.88 post-trenching (2.92km in shallow water area), KP7~KP3.8 post-trenching (6.4km in deep water area) crossing over point treatment and concrete block installation (36pcs), backfilling with excavated material (53,280m3) and cement sandbag (454m3) backfilling in nearshore section.


Chenghai 1-1 Platform Submarine Cable Laying Project (Year 2021-- CNPC)   Chenghai 1-1 Platform Submarine Cable Laying Project (Year 2021-- CNPC)   Chenghai 1-1 Platform Submarine Cable Laying Project (Year 2021-- CNPC)

Chenghai 1-1 Platform Submarine Cable Laying Project (Year 2021-- CNPC)   Chenghai 1-1 Platform Submarine Cable Laying Project (Year 2021-- CNPC)